Power system maintenancePlanned Maintenance

Description

The data center has scheduled power system maintenance in the listed locations. During the maintenance, data center engineers will perform the inspection of the electrical installation to ensure compliance with required standards. Unavailability of your servers is not expected.

Components

Power system

Locations

AMS2, AMS4, AMS5, AMS6

Schedule

March 30, 2026 05:00 - June 19, 2026 17:00 UTC



March 30, 2026 05:00 UTC
UPDATE

The scheduled maintenance has begun.
Power feed maintenancePlanned Maintenance

Description

The data center has scheduled power feed maintenance in the listed locations. During the maintenance, power generators of power feeds in these locations will be tested. Unavailability of your servers is not expected.

Components

Power system

Locations

LUX1, LUX2

Schedule

May 6, 2026 06:00 - 11:00 UTC



May 6, 2026 06:00 UTC
UPDATE

The scheduled maintenance has begun.
Power feed maintenancePlanned Maintenance

Description

The data center has scheduled power feed maintenance in the listed locations. During the maintenance, power generators of power feeds in these locations will be maintained. Unavailability of your servers is not expected.

Components

Power system

Locations

WAS3, WAS4

Schedule

May 21, 2026 11:00 - May 29, 2026 22:00 UTC



May 28, 2026 21:31 UTC
UPDATE

The data center postponed the scheduled maintenance due to technical reasons. The maintenance is now scheduled to continue on June 8 at 11:00 UTC and complete on June 12 at 21:00 UTC.

May 21, 2026 11:00 UTC
UPDATE

The scheduled maintenance has begun.
Power systemPlanned Maintenance

Description

The data center has scheduled power feed maintenance in the listed location. During the works, data center engineers will perform uninterruptible power supply (UPS) maintenance. Unavailability of your servers is not expected.

Components

Power system

Locations

LON1

Schedule

May 25, 2026 06:00 - June 1, 2026 18:00 UTC



May 26, 2026 09:04 UTC
UPDATE

The scheduled maintenance has begun.

Servers.com website




Operational

Portal - portal.servers.com




Operational

Ticket/e-mail system




Operational

Public network




Operational

Global Private Network




Operational

Direct Connect




Operational

Power system




Planned Maintenance

Cloud servers




Operational

Cloud storage




Operational

DNS resolver




Operational

Load balancers




Operational

Firewalls




Operational

Kubernetes




Operational

Public API




Operational

VPN to DRAC




Operational

VPN to Global Private Network




Operational

Authoritative DNS




Operational

Cooling system




Operational

Scheduled Maintenance

Power feed maintenancePlanned Maintenance

Schedule

June 1, 2026 00:00 - June 27, 2026 16:00 UTC

Components

Power system

Locations

SIN2

Description

The data center has scheduled power feed maintenance in the listed location. During the maintenance, power generators of power feeds in this location will be tested. Unavailability of your servers is not expected.
Power feed maintenancePlanned Maintenance

Schedule

June 1, 2026 11:00 - June 5, 2026 23:00 UTC

Components

Power system

Locations

MIA1

Description

The data center has scheduled power feed maintenance in the listed location. During the maintenance, uninterruptible power supply (UPS) in this location will be tested. Unavailability of your servers is not expected.

Schedule

June 2, 2026 07:00 - 13:00 UTC

Components

Portal - portal.servers.com, Public API, VPN to DRAC

Locations

AMS2, AMS4, AMS5, AMS6

Description

We have scheduled maintenance of the infrastructure servers in the listed locations. During the works, we will update the server software to improve service stability. Unavailability of your servers is not expected. However, we expect the impact described below: - unavailability of VNC console and server management via the portal.servers.com control panel and the Public API; - suspension of all pending processes in the portal.servers.com control panel (OS reinstallation, ordering new or changing current services) and their automatic resumption afterward; - unavailability of the VPN to DRAC service for up to an hour.

Schedule

June 2, 2026 09:00 - 15:00 UTC

Components

Portal - portal.servers.com, Public API, VPN to DRAC

Locations

SJC1

Description

We have scheduled maintenance of the infrastructure servers in the listed location. During the works, we will update the server software to improve service stability. Unavailability of your servers is not expected. However, we expect the impact described below: - unavailability of VNC console and server management via the portal.servers.com control panel and the Public API; - suspension of all pending processes in the portal.servers.com control panel (OS reinstallation, ordering new or changing current services) and their automatic resumption afterward; - unavailability of the VPN to DRAC service for up to an hour.
Power feed maintenancePlanned Maintenance

Schedule

June 3, 2026 05:00 - 17:00 UTC

Components

Power system

Locations

AMS2, AMS4, AMS5, AMS6

Description

The data center has scheduled power feed maintenance in the listed locations. During the maintenance, power generators of power feeds in these locations will be tested. Unavailability of your servers is not expected.
Power feed maintenance Planned Maintenance

Schedule

June 3, 2026 06:00 - 11:00 UTC

Components

Power system

Locations

LUX1, LUX2

Description

The data center has scheduled power feed maintenance in the listed locations. During the maintenance, power generators of power feeds in these locations will be tested. Unavailability of your servers is not expected.
Power system maintenancePlanned Maintenance

Schedule

June 3, 2026 06:00 - June 5, 2026 19:00 UTC

Components

Power system

Locations

LON1

Description

The data center has scheduled power system maintenance in the listed location. During the works, data center engineers will perform uninterruptible power supply (UPS) maintenance. Unavailability of your servers is not expected.

Schedule

June 4, 2026 07:00 - 13:00 UTC

Components

Portal - portal.servers.com, Public API, VPN to DRAC

Locations

DFW2, DFW3, DFW4, HKG1, LUX2

Description

We have scheduled maintenance of the infrastructure servers in the listed locations. During the works, we will update the server software to improve service stability. Unavailability of your servers is not expected. However, we expect the impact described below: - unavailability of VNC console and server management via the portal.servers.com control panel and the Public API; - suspension of all pending processes in the portal.servers.com control panel (OS reinstallation, ordering new or changing current services) and their automatic resumption afterward; - unavailability of the VPN to DRAC service for up to an hour.
Power feed maintenancePlanned Maintenance

Schedule

June 29, 2026 14:00 - July 4, 2026 02:00 UTC

Components

Power system

Locations

SJC1, SJC2, SJC3

Description

The data center has scheduled power feed maintenance in the listed locations. During the maintenance, power generators of power feeds in these locations will be tested. Unavailability of your servers is not expected.


May 27, 2026 17:09 UTC
UPDATE

The data center postponed the scheduled maintenance due to technical reasons. The maintenance is now scheduled on June 29, 2026 14:00 (UTC).
Power system maintenancePlanned Maintenance

Schedule

July 6, 2026 05:00 - July 9, 2026 18:00 UTC

Components

Power system

Locations

LON1

Description

The data center has scheduled power system maintenance in the listed location. During the works, the data center will perform maintenance of the power distribution system. Unavailability of your servers is not expected.


May 26, 2026 20:21 UTC
UPDATE

The data center postponed the scheduled maintenance due to technical reasons. The maintenance is now scheduled on July 6.